Getting a schedule into Brink
Schedules come from Primavera P6 XER exports.1
Pick the project
Set your active project first, from the project switcher in the top bar.
Schedules belong to a project — that’s what lets Brink diff each new export
against that project’s history.
2
Upload the XER
Go to the Documents page, click Upload files, and
choose your
.xer export. Brink recognises it and routes it into the
schedule pipeline rather than the normal document flow.3
Open the Schedule page
Your latest snapshot renders as a Gantt chart. Upload the next export the
same way and it becomes the new latest snapshot, diffed against the one
before it.
Re-uploading an export that’s byte-for-byte identical to the previous one
doesn’t create a new snapshot — nothing changed, so there’s nothing to diff.
Reading the chart
Activities are grouped by WBS. Each row shows the activity’s code and name on the left and its bar on the timeline, with the date range and either critical or its remaining float called out beside the bar. The legend explains the colours:Expand for the full picture
Click the chart, or the Expand button in the header, for a near-fullscreen view at a fixed day scale with a sticky activity column. Four summary cards sit above it:- Range — the schedule’s first start to its last finish
- Span — total days
- WBS groups — how many groups the schedule is broken into
- Critical — how many activities sit on the critical path
What changed between revisions
Each new export is compared against the previous one, and the differences are flagged as findings — worst first — and surfaced on your Daily page under On the schedule, as a banner reading “schedule revision flagged — N findings (M high) in the export file”. Brink looks for:Schedule on the Daily page
The On the schedule section of the Daily page shows the activities landing in the day or week you’re looking at, each tagged Schedule with its project, WBS, and finish date, flagged critical or with its remaining float — along with the revision banners described above.Which day is “today”?
Schedule days follow the jobsite’s calendar, not your browser’s. That comes from the project’s site timezone, falling back to your organization’s default. When the two differ, a Site time: … badge appears in the page header so you know which clock the days are being counted on.Asking about the schedule
Schedule data is part of your company brain, so you can ask about it directly in Chat:- “Which activities slipped in the latest schedule revision?”
- “What’s on the critical path in the next 30 days?”
- “Show me activities with negative float”